Site portrait

TelemaxX IPC6

Karlsruhe, BW · TelemaxX Telekommunikation GmbH · announced

Independent observatory

Site grade

C

probable grade · window B–E

Rated C on site; project data insufficient to grade project & process.

This page says the same thing as the technical sheet, in the order of a decision to take: what weighs, what is missing, and what is still worth asking for while it can still be asked.

Annotated aerial view of TelemaxX IPC6: footprint, watercourse and distances
Straight-line distances from the reference coordinate. The rings are distance buffers, not statutory zoning. Esri, Maxar, Earthstar Geographics · OpenStreetMap (ODbL)

The five pillars behind the grade

A pillar with no letter rests on too few measures to defend one. We publish the count rather than a letter we could not stand behind.

The points that will decide

Water

  • Water body status : water body in poor status
  • Local water stress : no measured water stress in the area

To ask for : Which cooling technology, and how much water a year — into an already impaired watercourse? to ask now, before the application is filed

Land & biodiversity

  • Overlap / distance to protected areas : protected natural area 1–5 km away
  • Soil status (artificialized / natural / agricultural) : previously developed land

To ask for : What ground footprint, and on which parcels? to ask now, before the application is filed

Energy

  • Local grid carbon intensity : 380.6 gCO2e/kWh

To ask for : What PUE is announced, and measured how? to ask now, before the application is filed

What this looks like from the street

Noise — continuous, day and night

Cooling runs permanently and standby generators are tested on a schedule. What is regulated is not a distance but how far the noise rises at the neighbour's.

The nearest recorded dwelling is 675 m from the reference point. That is a straight-line distance, never a noise measurement: the acoustic study in the file is still to be demanded — it is the one that sets enforceable values.

Standby generators and their fuel

A facility like this keeps standby generators and the tanks that feed them. They are what gets tested, what gets smelled, and what triggers its own permitting. Their number, their fuel and the volume stored are in the file where one exists.

We measure no health effect and we do not claim to. We publish what is in the file, and what is not.

What we have not measured

  • Grid connection capacity / proximitynot yet collected by us
  • Grid congestion / connection queuenot yet collected by us
  • Heat-network connectabilitynot yet collected by us
  • Basin withdrawal pressurenot yet collected by us
  • Ecological corridors (TVB)verified absent from the file we read
  • Municipality socio-economic profilenot yet collected by us
  • Absorption capacity (project size vs municipality)verified absent from the file we read
  • Technological hazard / nearby Seveso sitesverified absent from the file we read
  • Observed level of oppositionverified absent from the file we read
  • Elected officials' position (voted facts only)verified absent from the file we read

These gaps are ours, not the developer's: they say where our measurement stops, and they do not penalise the site.

Where the procedure stands

  1. announced
  2. under review
  3. under construction
  4. operating

the Land's Regierungspräsidium (immission-control permit), the municipality for the building permit

Once consent is granted or refused, its content, its conditions and the reasons behind it must be made public — including how the public's comments were taken into account.

The public concerned has a right of review before a court to challenge the decision's legality, on substance and on procedure. The deadline itself is set by each State — that is the national line to read.

An action against the permit must be brought within one month of its notification. After that it becomes final.

Any environmental information held by a public authority is available on request, without having to state an interest, and must be supplied within one month — two if the volume warrants it, the authority having to say so before the deadline.

Directive 2011/92/UE, art. 9(1) · Directive 2011/92/UE, art. 11(1) · VwGO § 74 Abs. 1 · Directive 2003/4/CE, art. 3(1) et 3(2)

What to get written into the approval

  • To ask for : Which cooling technology, and how much water a year — into an already impaired watercourse? to ask now, before the application is filed
  • To ask for : What PUE is announced, and measured how? to ask now, before the application is filed
  • To ask for : Will the waste heat be recovered, by whom, and from which phase? to ask now, before the application is filed
  • To ask for : What ground footprint, and on which parcels? to ask now, before the application is filed
  • To ask for : Which avoidance, reduction and offset measures? to ask now, before the application is filed
  • To ask for : Is the land already designated for development in a supra-municipal plan? to ask now, before the application is filed
  • To ask for : Does the planning document have to be changed for this project? to ask now, before the application is filed
  • To ask for : How many permanent jobs after construction, and of what skill level? to ask now, before the application is filed
  • To ask for : What tax revenue for the municipality, over what period, with what abatements? to ask now, before the application is filed
  • To ask for : What consultation is planned, on what date, and who answers it? to ask now, before the application is filed
  • To ask for : Is the full file open to consultation, where, and until when? to ask now, before the application is filed

Commitments that are not in the approval cannot be enforced: what is not written cannot be demanded later.

↔ Technical sheet — the measures one by one, their values and their sources